Report (Portfolio weather)

The Report screen gathers in a single grid the status reports of every project in the portfolio. Each row is a report; the columns are the indicators and the progress comments written by the project leaders.

Reach it from the Report menu of a project portfolio.

The columns

The columns are the fields of the Report entity: one date and five indicator / comment pairs.

ColumnContent
Report dateThe date the report was drawn up
Overall indicator / Overall updateThe general weather and its comment
Delivery indicator / Delivery updateThe deliverables side
Schedule indicator / Schedule updateThe timing side
Budget indicator / Budget updateThe financial side
Resource indicator / Resource updateThe capacity side

Indicators take the values Green, Amber, Orange and Red. The comments come from each project's Weather record — they are not entered here.

Latest project weather

This is the command specific to this screen. The Latest project weather switch, at the top of the grid, keeps only the most recent report of each project.

  • On — one row per project: the state of the portfolio right now, the review reading.
  • Off — every report of every project: the trajectory, report after report.

Turning it off and sorting on Report date is how you follow one project over time.

No automatic comparison between two dates

The screen shows no delta, no trend arrow, no comparison to one or three months back. The grid shows the reports; the chronological reading gives the trend.

Analysing, exporting

  • Sort and filter on any column — for instance isolate the red Overall indicator rows.
  • Group by dragging a header into the grouping bar.
  • Scenario — the funnel narrows the scope to a selection of projects. An orange badge on the button shows the number of unticked projects, hence missing from the list.
  • View settings (⚙️) — Column management, Display, Project hierarchy management.
  • ExportExcel (.xlsx) or CSV (.csv).
No PDF or PowerPoint export

The only formats offered are Excel and CSV. For a committee document, the practice is to export to Excel and lay it out in your presentation tool.

See also

Good habit

Keep Latest project weather on to open the review, then switch it off on the single project that is a problem, to unfold its history.