Global planning

The Global planning screen is the consolidated Gantt of a project portfolio: it shows all the projects in the portfolio on a single timeline, with their tasks, milestones, dependencies and baselines. It's the go-to view to steer a set of projects at a glance.

You reach it from the Portfolios → Global planning menu.

Don't mix them up
  • Planning — the Gantt of a single project (project manager's view).
  • Global planning — the Gantt of all projects in a portfolio, consolidated.

Anatomy of the screen

  • The project tree, on the left — the list of the portfolio's projects. Programs appear in orange. A value in parentheses indicates an ongoing simulated shift (see Shift simulation).
  • The consolidated Gantt, on the right — each project is shown as its own row / bar, with its milestones.
  • The toolbar, at the top — selection, zoom, filters, simulation, settings and exports.

The toolbar

ToolPurpose
ModeFor agile projects linked to Jira: switch the display by Sprint or by Epic
ZoomTimeline scale: Year / Quarter / Month / Week / Day
Select all / Clear selectionSelects or deselects all the portfolio's projects
Filter the displayed periodRestricts the visualized time window
Shift simulation of projectsSimulates shifting the projects (see below)
ProfileFilters the display by resource profile
⚙️ SettingsOpens the settings panel (see below)
Columns managerChooses the columns shown in the left grid
MoreSecondary actions and exports (PNG, PDF, Excel, CSV…)

Shift simulation of projects

The shift simulation lets you test the impact of postponing projects without altering the real data. The shift applied to each project is shown in parentheses in the tree. You preview the new planning, then:

  • Validate — actually applies the shifts
  • Close — discards the simulation

Settings (⚙️ Settings)

The Settings button opens a panel gathering all the display options of the consolidated planning.

Colors

Sets the coloring mode of the bars:

  • Classic — default color
  • By status (tasks and milestones) — colors by the status of tasks and milestones
  • By status (projects, tasks and milestones) — also colors projects by their status

Group by

Groups the portfolio's projects by an attribute (project field), to structure the planning by category.

Default project sort

Project display order:

  • Project name (alphabetical)
  • Earliest start date
  • Latest end date
  • Manual order (drag & drop) — appears once you have reordered projects by hand; a Reset button returns to the default sort and clears the manual order

Rollup (level of detail)

Controls the depth displayed in the consolidated Gantt:

  • Project — a single bar per project (most synthetic view)
  • Task (Level 1) — expands first-level tasks
  • Task (Level 2) — expands down to the second level

The rollup change is only applied when the panel is validated, to avoid the planning moving while you adjust options.

Overlaid displays

Four toggles enable / disable information layers:

ToggleEffect
BaselinesShows the baselines (initial planning) to compare with actuals
ActualOverlays the real progress on the bars
Critical pathHighlights the sequence that drives the projects' end
Week numberAdds the week number on the timeline

Project priority

Two options based on the project's Priority field (levels 1 to 5, set in the project definition).

Show the project priority as a badge next to its name adds a colored pill to the right of the project name — in the planning tree as well as in the resource grid at the bottom of the screen.

BadgePriority
🔴 1Highest
🟠 2High
🟡 3Medium
🟢 4Low
🟩 5Lowest

Projects with no priority set carry no badge.

Diagram display drives the resource workload histogram (bottom part):

  • Workload and overload — the usual display;
  • Breakdown by project priority — the bar is split into colored segments, one per priority, each proportional to the workload coming from the projects at that priority. Segments stack from the bottom (priority 1 first), a dashed line marks capacity — anything above it is overload — and the tooltip details the workload priority by priority.

The "Other projects" rows gather projects of mixed priorities: they keep the workload / overload display.

Grouping by priority

Priority is also available as a criterion in Group by and in the project hierarchy management: projects are then gathered under one node per priority level.

Spacing

Adjusts the row height of the planning (display density).

Milestone label position

Sets the orientation of the milestone label:

  • Horizontal
  • Horizontal right
  • Diagonal
  • Invisible (hides the label)

A separate setting, Milestone label position for the first project, applies a different orientation to the first project in the list (useful when its milestone is near the edge).

Grid columns

The Columns manager lets you show the desired attributes in the left grid (name, dates, progress, owner, custom fields…). The layout can be saved in a favorite.

Exporting

The More menu offers exporting the consolidated planning (PNG, PDF, Excel, CSV) to share it in portfolio or steering committees.

See also

Good habit

Start in Project rollup for an overview, then switch to Task (Level 1) on critical projects. Set a baseline before each committee to objectively measure slippage from one portfolio review to the next.